Redevelopment Update 20 May

The redevelopment continues to progress well. As with any building works there have been a few issues that have had to be dealt with as we go along – most noticeably a downpipe was disconnected and flooded the parquetry floor. The builders have worked to effect a temporary fix and will fix permanently as the works progress.
This couple of weeks progress is as follows:

  • Concrete pour to eastern stair followed by strip and clean.
  • Steelwork will arrive on site and installation will continue for the week.
  • Supporting formwork to first floor slab will be stripped and removed except for the formwork on the front balcony.
  • Site clean up.
  • Excavator to be removed ASAP.
  • Lift will be delivered and installed
  • Installation of roofing will commence later in the week.